Here are the baseline requirements needed in order to proceed with a steam turbine project:
-
1. Minimum steam flow of 5000 lbs/hr
-
2. Minimum inlet pressure of 100 PSIG
-
3. Minimum pressure ratio of 2:1 (inlet/outlet steam)
-
4. Minimum capital investment of $150K plus install costs
-
5. Power out is maximized by maximizing the pressure ratio
If your project meets these requirements, then we should further analyze your situation and determine the types of results you can expect. Give us a call.
Gas turbine projects require a far greater level of analysis. Give us a call to explore further.